What is a Construction Change Directive (CCD)?

Construction projects often require modifications to the original scope, schedule, or cost due to unforeseen conditions or owner requests. When these necessary alterations arise, formal documentation is required to adjust contract terms and maintain project momentum. A Construction Change Directive (CCD) is a specific, formal document used to authorize work to proceed immediately when a change is needed but the full financial and time implications have not yet been mutually agreed upon.

Defining the Construction Change Directive

A Construction Change Directive is a written instruction issued by the project owner or the architect, directing the contractor to proceed with a modification to the work. It is distinct because it is issued before the parties have reached a final agreement on the resulting adjustments to the contract sum or time. The CCD is a unilateral directive, meaning the contractor is legally obligated to execute the change immediately upon receipt, even without signing the document. This mandatory action is authorized by the underlying construction contract, such as the General Conditions, ensuring that a dispute over pricing does not halt the physical progress of the work.

The Specific Role of a CCD in Project Management

The primary purpose of issuing a CCD is to prevent project delays when time is a concern. This directive is employed when an immediate change is required to keep the construction schedule on track, such as addressing an unforeseen site condition or correcting a design conflict. The CCD acts as temporary authorization when the parties cannot reach a swift consensus on the cost or time extension. By immediately directing the work, the CCD prevents negotiations over scope or price from escalating into costly project stoppages. It maintains momentum, allowing the determination of cost and time to occur concurrently with the physical execution of the changed work.

Comparing the CCD to Other Change Documents

Construction projects utilize different documents to manage modifications, depending on the level of agreement reached and the impact of the change. The CCD is one of three primary methods for formally altering the contract, each with distinct authorization requirements. The differences center on who signs the document and whether the contract sum or time is affected. Understanding these distinctions is fundamental to proper contract administration.

Change Orders (CO)

A Change Order (CO) represents a formal, bilateral agreement that modifies the construction contract. This document requires the signature of all three principal parties: the owner, the contractor, and the architect. The CO confirms the agreed-upon adjustments to the scope of work, the contract sum, and the contract time, making it a binding amendment to the original contract. Because a Change Order requires mutual consensus, it is only issued once all terms related to the change have been fully negotiated.

Minor Changes in the Work

Minor Changes in the Work refer to modifications that do not affect the contract sum or the contract time. These changes are often administrative, involve clarification, or detail a minor design adjustment within the established scope. Such changes are authorized solely by the architect through a document like an Architect’s Supplemental Instruction (ASI). Since these adjustments do not alter financial or scheduling commitments, they require only the architect’s signature to be implemented.

Required Elements and Issuance Process

The procedural foundation for a CCD is established in the construction contract, often outlined in the General Conditions. When formally issued, the CCD must contain a clear, detailed description of the work, including any necessary drawings or specifications. It must also specify the method proposed for determining the contractor’s compensation. This compensation method might be based on unit prices established in the contract, a negotiated lump sum, or, most commonly, a time and materials basis. The document is signed by the owner and the architect, but the contractor’s signature is not required for the directive to be effective. Issuance formally directs the contractor to proceed immediately, reserving the final determination of cost and time for a later date.

Converting a CCD into a Change Order

A CCD is a temporary measure, and the work directed by it must eventually be resolved into a final, binding agreement. The process begins with the contractor submitting a detailed proposal that quantifies the actual cost incurred and the required extension of time. This proposal is based on the compensation method stipulated in the directive, such as itemized documentation for labor and materials if executed on a time and materials basis. The owner and contractor then negotiate to finalize the cost and time adjustments. If they reach an agreement, the CCD is formally closed out by issuing a Change Order, which incorporates the agreed-upon sum and schedule adjustment into the contract. If the parties fail to agree on the final price or time, the contract allows the architect to make an interim determination of the justified cost. The contractor must still perform the work as directed and retains the right to pursue any remaining disputed amount through formal dispute resolution, such as mediation or arbitration.

Post navigation