A Guaranteed Maximum Price (GMP) contract is a widely used method in the construction industry that sets a ceiling on the total cost an owner will pay for a project. This hybrid approach balances the owner’s need for cost certainty with the flexibility required for complex projects that may begin before the design is fully complete. The GMP mechanism promotes collaboration by aligning the financial incentives of the owner and the contractor around cost control and project execution.
Defining the Guaranteed Maximum Price Contract
The GMP contract is a cost-reimbursable agreement where the contractor is paid the actual cost of the work performed, plus a pre-determined fee for overhead and profit. The defining characteristic is the inclusion of a maximum price limit that the contractor guarantees the total cost billed to the owner will not exceed. This ceiling transfers the financial risk of cost overruns, excluding owner-directed scope changes, from the owner to the contractor. This arrangement requires an open-book accounting process, allowing the owner to review all project costs. GMPs are common in delivery methods like Construction Manager at Risk (CMAR), where the contractor is brought in early to influence design and estimating.
The GMP is a firm commitment. If the final costs incurred by the contractor surpass the maximum price, the contractor must absorb the excess cost. This creates a financial incentive for the contractor to manage the budget diligently throughout the construction phase. Conversely, if the actual costs are less than the guaranteed maximum price, the difference, known as savings, is typically returned to the owner or shared based on a negotiated ratio.
How the GMP Contract Structure Works
The operational mechanics of a GMP contract revolve around two figures: the Guaranteed Maximum Price and the Actual Cost of Work. The GMP represents the upper financial limit, calculated based on detailed estimates of labor, materials, subcontractor bids, and the contractor’s fee. The Actual Cost of Work includes the direct expenses the contractor incurs, such as payroll, material invoices, and equipment rentals. The owner reimburses the contractor for these actual costs as they occur, up to the maximum price ceiling.
A core feature is the “Shared Savings” clause, which addresses when the Actual Cost of Work comes in below the established GMP. Any realized savings are split between the owner and the contractor according to a pre-negotiated percentage, such as 50/50 or 60/40. This arrangement rewards the contractor for finding efficiencies and value engineering solutions during construction.
The handling of cost overruns provides the owner with budget protection. Costs that exceed the GMP become the responsibility of the contractor, potentially reducing their profit margin. The only exception is when the owner formally approves a change order that expands the project’s scope, necessitating an increase in the GMP. This firm cap places the burden of accurate estimating and risk management on the contractor.
Key Components of the GMP Calculation
The final Guaranteed Maximum Price is a detailed summation of various cost elements covering every aspect of the project. This structured breakdown provides transparency to the owner. The calculation includes direct construction costs, the contractor’s fixed fee for overhead and profit, and specific allowances for future costs. Three distinct components are regularly included in the final GMP figure to account for uncertainty and project management.
Contingency
Contingency is a dedicated fund included within the GMP to cover unforeseen issues, minor errors, or scope gaps during construction. This buffer is set aside for “known unknowns,” such as design conflicts or minor site conditions that could not be fully predicted during estimating. The contingency amount is typically controlled by the contractor, but its use must be justified and often requires formal owner approval.
If the project is completed without fully utilizing the contingency fund, the remaining balance is usually treated similarly to project savings. The unspent portion may be returned entirely to the owner or incorporated into the shared savings calculation, depending on the contract’s terms. Contingency allows the contractor to absorb minor, unexpected costs without requiring a formal change order to increase the overall GMP.
General Conditions
General Conditions represent the non-labor and non-material costs necessary for the overall management and operation of the construction site. These expenses cannot be tied to a specific line item of construction work but are required to complete the project. Examples include temporary utilities, site security, field office trailers, safety equipment, and the salaries of site-based personnel, such as the project superintendent.
These costs are detailed and budgeted upfront as part of the GMP, ensuring the owner has visibility into the contractor’s operational expenses. The General Conditions budget is an estimate. If the actual costs come in below the budgeted amount, the difference contributes to the project savings.
Allowances
Allowances are placeholder amounts included in the GMP for specific items whose final selection, scope, or cost is not known when the contract is signed. They are commonly used for finish materials, fixtures, or equipment where the owner is still considering different options. For instance, a contract might include an allowance for light fixtures or specific flooring materials.
Once the owner makes the final selection, the actual cost of the item is compared against the initial allowance amount. If the chosen item costs less than the allowance, the difference is deducted from the GMP, resulting in savings. If the selected item costs more, the owner must pay the difference, which results in a change order to increase the GMP.
Advantages and Disadvantages for the Owner
The primary advantage of the GMP structure is the establishment of budget certainty before the project is fully designed or constructed. By setting a maximum price, the owner is shielded from unexpected cost increases, significantly reducing financial risk exposure. This price cap allows for more reliable financial planning and secures funding with confidence in the final project cost.
The GMP model also facilitates early contractor involvement, often referred to as pre-construction services. Bringing the contractor in during the design phase allows them to provide valuable input on constructability, cost estimates, and value engineering. Furthermore, the potential for shared savings creates an incentive for the contractor to be efficient, potentially leading to a final cost lower than the guaranteed maximum.
A potential disadvantage is the risk of the contractor inflating the initial GMP estimate. Because the contractor assumes the risk of cost overruns, they may pad the contingency or be overly conservative in their estimates. This practice can result in the owner paying a higher initial price than they might have under a competitive bid process. Since the GMP contract is often negotiated rather than competitively bid, price competition may be limited.
Advantages and Risks for the Contractor
Contractors benefit from the GMP model due to early participation, often during the pre-construction phase. This involvement allows the contractor to influence the design and material selection, enabling them to proactively manage costs and buildability. They gain a deeper understanding of the project’s complexities, helping them mitigate potential issues before they become expensive problems.
The inclusion of a shared savings clause provides the contractor with a direct financial incentive to perform efficiently. If the contractor keeps the actual costs below the guaranteed maximum price, they receive a share of the remaining funds as an additional profit bonus. This structure encourages innovation and lean construction practices, as every dollar saved contributes to the contractor’s bottom line.
The primary risk for the contractor is assuming financial liability for cost overruns not caused by owner-directed changes in scope. If the contractor miscalculates material costs, underestimates labor hours, or encounters unforeseen conditions not covered by contingency, they must cover these expenses. This risk requires the contractor to invest heavily in detailed and accurate estimating and to implement robust cost-tracking and risk management systems.
Comparing GMP to Other Common Contract Types
The Guaranteed Maximum Price contract offers a unique balance compared to other contract types, such as Lump Sum and Cost Plus Fixed Fee. This model combines the cost certainty of a fixed price with the flexibility and transparency of a cost-reimbursable structure. Understanding these differences is helpful when selecting the appropriate contract for a project.
A Lump Sum, or Fixed Price, contract requires the contractor to agree to a single, set price for the entire scope of work, regardless of the actual costs incurred. This offers the owner maximum price certainty but requires the project design to be 100% complete before bidding. Unlike the GMP, it provides no opportunity for the owner to realize cost savings if the project comes in under budget.
The Cost Plus Fixed Fee contract reimburses the contractor for all actual project costs plus a set fee for profit, with no defined cost ceiling. This exposes the owner to unlimited financial risk, as they must pay for all overruns, even those caused by contractor inefficiency. While both the Cost Plus and the GMP models offer cost transparency, the GMP eliminates the owner’s risk of unlimited overruns by imposing the price cap.
When to Use a Guaranteed Maximum Price Contract
A Guaranteed Maximum Price contract is best suited for projects requiring budget certainty but needing to begin construction before the design documents are fully finalized. This is common in “fast-track” projects where overlapping the design and construction phases is necessary to meet an aggressive schedule. The GMP allows the project to move forward quickly while providing the owner with a financial safeguard against excessive costs.
The contract is also appropriate for large, complex projects where the scope is well-defined but potential risks necessitate a contingency buffer. Projects utilizing the Construction Manager at Risk (CMAR) delivery method frequently incorporate a GMP, leveraging the contractor’s early involvement to manage costs and complexity. The GMP contract provides the ideal framework when the owner values collaboration, transparency, and a financial incentive for the contractor to achieve cost savings.

