What Is an EPC Agreement: Components and Risk Transfer

An Engineering, Procurement, and Construction (EPC) agreement is a contractual structure used for executing complex, large-scale industrial projects, often in sectors like energy, infrastructure, and heavy manufacturing. The EPC model manages the entire development process of a facility, from initial design through to final commissioning. This framework is valued in project finance because it provides a clear mechanism for managing and mitigating the substantial risks inherent in building large assets.

Defining the Engineering, Procurement, and Construction Contract

The defining characteristic of an EPC contract is single-point responsibility, which simplifies execution for the project owner. The owner enters into a single contract with the EPC Contractor, who assumes the comprehensive obligation for the project’s successful delivery. The contractor integrates all aspects of the facility’s development, ensuring a unified approach across different phases. The agreement covers the entire lifecycle, beginning with detailed design and concluding upon the successful handover of a fully operational asset. This structure places the burden of coordination and execution entirely on the contractor.

The Three Core Components of an EPC Agreement

The scope of work within an EPC agreement is divided into three distinct components that define the contractor’s duties.

The Engineering Scope involves translating the owner’s requirements into detailed construction drawings and technical specifications. This phase includes process flow diagrams, equipment layouts, civil and structural designs, and preparing technical documentation necessary for regulatory compliance. The contractor is also responsible for securing design-related permits required before construction can begin.

Following the design finalization, the Procurement Scope manages the acquisition of all necessary materials, equipment, and services required to build the facility. This involves identifying suitable vendors, negotiating purchase orders, expediting the fabrication process, and managing the logistics of global transportation. The contractor must ensure all procured items meet the precise technical specifications defined in the engineering phase and arrive at the site on a schedule that supports the construction timeline.

The final phase, the Construction Scope, involves all on-site activities necessary to erect and install the facility. This work includes site preparation, foundation pouring, the physical erection of structures, installation of all mechanical and electrical equipment, and piping. The construction phase culminates in mechanical completion, which signifies that all physical work is complete and the plant is ready to move into the final stages of testing and commissioning.

The Lump Sum Turnkey Model and Risk Transfer

EPC contracts are structured around the Lump Sum Turnkey (LSTK) model, which is the primary mechanism for transferring project risk. The “Lump Sum” aspect means the contractor agrees to a fixed, predetermined price for the entire scope of work, regardless of any unexpected increases in costs for labor, materials, or subcontractors. This fixed price places the financial risk of cost overruns squarely on the contractor’s balance sheet.

The “Turnkey” aspect signifies that the contractor must deliver a facility that is complete, fully functional, and ready to operate at specified performance levels. This structure protects the owner from financial exposure and execution delays, transferring schedule delay risk to the contractor. This commercial structure provides budget certainty for the owner, which is a major factor in securing project financing.

Key Advantages of EPC for Project Owners

The defined risk structure of the EPC model provides the project owner with a high degree of certainty across the project’s lifecycle. Owners gain significant cost certainty due to the fixed-price nature of the lump sum agreement, making financial planning and investment decisions predictable. The contractual guarantee of a specific completion date provides schedule certainty, which is important for revenue forecasting.

Owners also benefit from performance certainty, as the contract guarantees the plant will function according to agreed-upon operational metrics. By delegating full responsibility to the EPC Contractor, the owner can focus resources on securing financing and preparing for the commercial launch of the completed facility.

Distinguishing EPC from EPCM and Other Contract Structures

While the EPC model transfers maximum risk to the contractor, other contract structures exist, such as Engineering, Procurement, and Construction Management (EPCM), which fundamentally change the allocation of responsibility. In an EPCM arrangement, the contractor acts as a professional agent, providing design, procurement support, and construction oversight services to the owner. The EPCM contractor does not guarantee the final project price or schedule, nor do they take on execution risk.

Under the EPCM model, the project owner retains responsibility for managing all individual trade contracts with suppliers and subcontractors. The owner assumes the full risk of cost overruns, schedule delays, and performance integration issues. The EPCM contractor is paid a fee for services, contrasting with the EPC contractor, who assumes the risk of profit or loss based on the fixed lump sum price. The choice between EPC and EPCM depends on the owner’s risk appetite and internal project management capabilities.

Critical Contractual Guarantees and Performance Testing

The effectiveness of risk transfer in an EPC contract is enforced through contractual guarantees and rigorous testing procedures. These agreements legally bind the contractor to deliver a facility that meets specific, measurable performance metrics, such as guaranteed output capacity, thermal efficiency, or operational reliability. The contract specifies a detailed program of performance testing, which takes place after mechanical completion and commissioning, to verify the plant’s operating characteristics.

If the facility fails to meet guaranteed performance targets or is delivered later than the agreed-upon date, the owner applies Liquidated Damages (LDs) against the contractor. Schedule LDs are calculated based on a daily rate for each day of delay, compensating the owner for lost revenue opportunity. Performance LDs are applied if the facility operates below guaranteed metrics, reducing the final contract price. This mechanism ensures the contractor has an incentive to meet both the schedule and the technical specifications.