What Is Earned Value? Measure Project Performance.

Earned Value Management (EVM) is an integrated technique used in project management to objectively measure performance and progress. It connects project expenditures to the actual work accomplished, moving beyond simple tracking of time or money spent. This methodology provides a unified view of the project’s scope, schedule, and cost status at any given point. EVM answers the fundamental question for stakeholders: “What did we get for the money we spent?”

Defining the Three Core Earned Value Metrics

The framework of earned value analysis relies on three fundamental data points tracked throughout a project’s life. These measurements serve as the raw inputs for all subsequent calculations and allow for a precise evaluation of project status.

Planned Value (PV) represents the authorized budget planned to be spent for the work scheduled to be completed up to a specific status date. PV is derived directly from the project schedule and the approved budget. It reflects the cumulative cost of the work items that should have been finished by that time, establishing a baseline expectation.

Actual Cost (AC) is the total cost incurred and recorded for the work performed up to the status date. AC includes all direct and indirect expenses, such as labor, materials, and overhead, that have been paid or accrued. This metric is tracked through the project’s accounting system and represents the real-world investment made.

Earned Value (EV) is the budgeted cost of the work actually performed and completed by the status date. EV is the value of the completed work expressed in terms of its original budget, not simply the amount of money spent. For instance, if a task was budgeted for \$1,000 and is 50% complete, the Earned Value is \$500, regardless of the actual money spent. This metric is the objective link between the work accomplished and the allocated budget.

Measuring Immediate Performance with Variance Analysis

Variance analysis assesses the immediate health of the project by calculating the absolute dollar difference between planned and actual performance. These variances offer a snapshot of project status, alerting managers to deviations from the baseline.

Cost Variance (CV) measures the difference between the value of the work performed (EV) and the actual cost incurred (AC). The formula is $\text{CV} = \text{EV} – \text{AC}$. A positive CV indicates the project is under budget, while a negative CV signals a cost overrun where actual spending exceeds the budgeted value of the work accomplished.

Schedule Variance (SV) measures the difference between the value of the work performed (EV) and the value of the work planned (PV). This variance is calculated as $\text{SV} = \text{EV} – \text{PV}$. A positive SV means the project is ahead of schedule, having completed more work than planned. A negative SV indicates the project is behind schedule.

For example, if $\text{PV} = \$15,000$, $\text{EV} = \$12,000$, and $\text{AC} = \$14,000$:
The Cost Variance is $\text{CV} = \$12,000 – \$14,000 = -\$2,000$ (over budget).
The Schedule Variance is $\text{SV} = \$12,000 – \$15,000 = -\$3,000$ (behind schedule).

Assessing Project Efficiency with Performance Indices

Performance indices transition the analysis from absolute dollar amounts (variances) to efficiency ratios. These indices are predictive because they show the rate at which the project is utilizing its budget and schedule resources. They provide a normalized measure of performance applicable across projects of any size.

The Cost Performance Index (CPI) measures budget efficiency for the work completed. The formula is $\text{CPI} = \text{EV} / \text{AC}$. This index shows how much value is earned for every dollar spent. A CPI greater than 1.0 is favorable, meaning the project is receiving more value than the cost incurred. A CPI less than 1.0 indicates a cost overrun and poor budget efficiency.

The Schedule Performance Index (SPI) measures the project’s progress efficiency relative to the plan. The calculation is $\text{SPI} = \text{EV} / \text{PV}$. An SPI above 1.0 signifies that the project is progressing faster than planned. Conversely, an SPI below 1.0 means the project is experiencing delays and completing less work than originally scheduled.

Predicting Project Outcomes Through Forecasting

EVM uses calculated efficiency metrics to forecast the final outcome of the project. This analysis leverages current performance trends to predict the ultimate cost and schedule, allowing stakeholders to make informed decisions.

The Budget at Completion (BAC) is the total approved budget for the entire project scope. BAC represents the original, planned cost target against which all performance and final cost predictions are measured.

The Estimate at Completion (EAC) is the forecasted total cost of the project when all work is finished. This dynamic figure replaces the static BAC when performance data suggests the original budget is unrealistic.

Calculating Estimate at Completion (EAC)

Two primary methods are used to calculate EAC:

1. Assuming Future Work is Efficient: This method assumes future work will be performed at the original budgeted rate. The calculation is Actual Cost plus the remaining budget: $\text{EAC} = \text{AC} + (\text{BAC} – \text{EV})$.
2. Assuming Current Inefficiency Persists: This common approach assumes the current cost inefficiency will continue. The formula divides the total budget by the current Cost Performance Index: $\text{EAC} = \text{BAC} / \text{CPI}$.

The Estimate to Complete (ETC) is the amount of money needed from the status date onward to finish the remaining work. ETC is the remaining expenditure required and is calculated by subtracting the Actual Cost from the Estimate at Completion: $\text{ETC} = \text{EAC} – \text{AC}$.

Setting Up and Implementing EVM

Successful EVM implementation requires a structured planning process that integrates scope, schedule, and budget. The initial step involves defining the project scope and organizing the work into manageable pieces using a Work Breakdown Structure (WBS). The WBS breaks the project into work packages, which are the lowest level where cost and schedule are tracked.

Next, a detailed project schedule must be established, assigning the budget to each work package over the timeline. This process creates the Performance Measurement Baseline (PMB), which is the time-phased budget against which all performance is measured. The PMB is the sum of all Planned Value (PV) across the project life cycle.

A key step is defining the rules for earning value, which dictates when work is officially credited as complete. Common methods include the 50/50 rule or the use of fixed formulas for short-duration tasks. Regular collection of actual cost and physical progress data is necessary to ensure EVM metrics remain accurate throughout the execution phase.

Strategic Advantages of Using Earned Value Management

Adopting an EVM framework offers several strategic advantages beyond simple expenditure tracking. It provides an objective, quantifiable measurement of project progress, replacing subjective status reports with integrated data on cost and schedule performance. This objectivity allows stakeholders to base decisions on verified facts.

EVM operates as an early warning system, detecting deviations in cost and schedule performance before they escalate into major problems. By consistently calculating the Cost Performance Index and Schedule Performance Index, managers can identify failing trends and intervene proactively. This foresight enables effective management of project resources.

EVM also improves communication by providing a common, standardized language for project status. Quantifiable metrics like CPI and EAC simplify complex performance into easily understood ratios and forecasts, building confidence and facilitating informed discussions.